What is a goods receipt note (GRN)? Format and process

A GRN records what actually arrived from a supplier against a purchase order. What it should contain, how partial deliveries and quality checks work, and the PO–GRN–invoice three-way match.

A goods receipt note (GRN) is the record that goods have arrived from a supplier: what came, how much, against which purchase order, and where it was stored. It's what turns a purchase order into stock. It's also what your accountant checks the supplier's bill against before paying.

What a GRN should contain

Field Example
GRN number and date GRN-0042, 23 Nov
Purchase order PO-0118
Supplier and their challan or invoice number Acme Steel, DC-77
Items and quantities received 2 mm steel sheet, 600 kg (ordered 1,000 kg)
Batch, expiry or serial numbers Heat no. H-2291
Warehouse or godown Pune plant
Received by Ravi (store)
Quality status Accepted, or held for inspection

The process, step by step

  1. Check the delivery against the PO. Right item, right supplier, quantity not more than what's still due.
  2. Count or weigh what actually arrived. The challan says 1,000 kg; the weighbridge says 985 kg. Record 985.
  3. Record batch or serial numbers for tracked items.
  4. Inspect, if the item needs it. Goods waiting for inspection shouldn't be usable stock yet.
  5. Post the GRN. Stock goes up in that godown, and the PO shows what's still to come.
  6. Match the bill. When the supplier's invoice comes, compare it with the PO (price) and the GRN (quantity) before paying.

Partial deliveries

Suppliers often deliver in parts: 600 kg today, 400 kg next week. Each delivery gets its own GRN against the same PO. The PO stays "partially received" until everything has arrived, so you always know what's still pending, and the supplier's real lead time can be measured from each receipt.

The three-way match

Before paying a supplier, check three documents agree:

  • Purchase order: what you agreed to buy, at what price.
  • GRN: what actually arrived and was accepted.
  • Supplier invoice: what they're asking you to pay.

If the invoice says 1,000 kg but the GRN says 985 kg, you pay for 985. Without GRNs, factories routinely pay for short deliveries and rejected material.

Quality hold

For items that need inspection (castings, chemicals, packaging with print specs), receive them into a quality hold rather than straight into usable stock. Once checked, the accepted quantity moves into the warehouse and the rejected quantity is written off or returned, both on record.

How KnowyourInventory handles GRNs

Receive goods against a purchase order, in one delivery or several. Each receipt gets a GRN number, goes straight into the order's warehouse with its batches or serials, and updates what's still due. Items marked for inspection go into Quality hold until passed. Supplier bills are recorded against the order, and each supplier's real lead time and on-time rate come from the receipts. You can even tell ChatGPT: "We received 600 kg of steel sheet from Acme on PO-0118."

Frequently asked questions

What is a GRN in inventory?

A goods receipt note records goods received from a supplier: the items, quantities, purchase order, batch or serial numbers, warehouse, and who received them. Posting it increases stock.

What is the difference between a GRN and a delivery challan?

The delivery challan comes from the supplier and says what they sent. The GRN is your own record of what you actually received and accepted, which may be less.

Can one purchase order have several GRNs?

Yes. Each partial delivery gets its own GRN against the same purchase order until the full quantity has arrived.

What is the three-way match?

Checking that the purchase order, the goods receipt note and the supplier's invoice agree on item, quantity and price before paying the supplier.