· 4 min read · Waseem
How to calculate a reorder point (with a worked example)
Reorder point = average daily usage × lead time in days + safety stock. A step-by-step example for an Indian factory, and the mistakes that make it wrong.
The reorder point is the stock level at which you place a new purchase order, so the material arrives before you run out. The formula is:
Reorder point = average daily usage × lead time (days) + safety stock
If you use 40 kg of steel sheet a day, your supplier takes 7 days to deliver, and you keep 120 kg as a buffer, your reorder point is 40 × 7 + 120 = 400 kg. When stock drops to 400 kg, you order.
Worked example
A Pune fabrication shop uses 2 mm steel sheet for wall brackets.
| Input | Value | Where it comes from |
|---|---|---|
| Average daily usage | 40 kg | Last 12 weeks of issues ÷ working days |
| Lead time | 7 days | From placing the PO to the sheet being in your store |
| Safety stock | 120 kg | Buffer for late deliveries and busy weeks (how to calculate it) |
- Demand during lead time: 40 kg × 7 days = 280 kg. That's what you'll use while waiting for the delivery.
- Add safety stock: 280 + 120 = 400 kg.
- Set it on the item: when stock in that godown reaches 400 kg, raise the order.
How much to order is a separate question. A simple rule is to order enough to cover the lead time plus your review period, then bring stock back up; KnowyourInventory suggests the quantity from the forecast and drafts the purchase order for you.
Getting the inputs right
Use working days, not calendar days. If the factory runs 26 days a month, average usage = monthly usage ÷ 26. Mixing calendar-day lead times with working-day usage understates the reorder point.
Measure lead time from the PO, not from dispatch. Lead time is order placed → goods received and checked. If inspection takes two days, include them.
Use real lead times, not the supplier's promise. A supplier who says 5 days but averages 8 will run you out of stock. Track it per supplier from your goods receipts.
Calculate it per godown. If Pune and Chakan both hold steel, each needs its own reorder point based on its own usage.
Revisit it. Usage changes with orders and seasons. A reorder point set a year ago is usually wrong; recalculate monthly, or let software do it from recent demand.
Common mistakes
- No safety stock. Then any delay means a stock-out. With safety stock of zero you run short in roughly half of all order cycles: every time usage during the lead time is above average.
- Ignoring stock already on order. If a PO for 500 kg is already on its way, you don't need another one. Compare available stock (on hand + on order − reserved for open orders) with the reorder point.
- Ignoring reservations. Material reserved for a production order you've already planned isn't really available. Subtract it.
- One number for the whole company. Different godowns, different usage, different reorder points.
How KnowyourInventory does it
Each item gets a reorder point per warehouse from its last 12 weeks of real usage, the supplier's measured lead time and a safety-stock buffer. The Reorder tab lists what to buy now, with the reason and the numbers behind each suggestion, holds back items that already have months of stock, and drafts the purchase orders. Or ask ChatGPT: "What should I reorder at the Pune plant this week?"
Frequently asked questions
What is the formula for reorder point?
Reorder point = average daily usage × lead time in days + safety stock. For 40 kg a day, a 7-day lead time and 120 kg safety stock, the reorder point is 400 kg.
What is the difference between reorder point and reorder level?
They mean the same thing in most factories: the stock level that triggers a new order. Some textbooks use "reorder level" for a fixed minimum set by hand and "reorder point" for one calculated from usage and lead time.
What is the difference between reorder point and safety stock?
Safety stock is the buffer you keep for delays and demand spikes. The reorder point includes it: it's the demand during the lead time plus the safety stock.
How often should I recalculate the reorder point?
At least monthly, and whenever usage or a supplier's lead time changes noticeably. Inventory software can recalculate it from recent demand automatically.