· 4 min read · Waseem
What is a bill of materials (BOM)? A guide for manufacturers
A bill of materials lists every raw material and part, with quantities, needed to make one unit of a product. How to write one, cost it in rupees, and use it to plan production.
A bill of materials (BOM) is the list of every raw material, part and sub-assembly, with quantities, needed to make one unit of a product. It's the recipe your factory follows. With a correct BOM you can tell, before you start, whether you have the material for an order, what each unit costs, and how much stock a production run will use.
A simple example
A steel wall bracket:
| Material | Quantity per bracket | Unit cost | Cost per bracket |
|---|---|---|---|
| Steel sheet 2 mm | 1.2 kg | ₹72/kg | ₹86.40 |
| M8 bolt | 4 pcs | ₹3/pc | ₹12.00 |
| Red enamel paint | 0.05 L | ₹260/L | ₹13.00 |
| Material cost | ₹111.40 |
To make 100 brackets you need 120 kg of sheet, 400 bolts and 5 L of paint. If the store has 90 kg of sheet, you know today, not halfway through the run, that you're 30 kg short.
What a good BOM includes
- Every input, including the small ones (fasteners, packing material, labels). The ₹2 item is usually the one that stops dispatch.
- Quantities per one unit of the finished product, in the unit you stock it in (kg, m, pcs, L).
- Scrap or yield allowance. If 1.0 kg ends up in the bracket but cutting wastes 0.2 kg, the BOM says 1.2 kg.
- By-products, if any (steel offcuts you sell or reuse).
- Operations (optional): cutting 2 minutes, pressing 1 minute, painting 3 minutes, at which work centre. This turns the BOM into a routing, used for labour and machine cost and for scheduling.
Single-level and multi-level BOMs
A single-level BOM lists only direct inputs. A multi-level BOM includes sub-assemblies with their own BOMs: a control panel uses an enclosure, and the enclosure has its own BOM of sheet, hinges and gaskets. Most small factories start single-level and add sub-assemblies as separate products with their own recipes.
Costing a product from its BOM
Product cost = material cost (from the BOM) + conversion cost (operation time × work centre rate) + overhead.
For the bracket: ₹111.40 material + 6 minutes of press and paint time at ₹540/hour (₹54) + ₹5 overhead = ₹170.40 per bracket. If you sell at ₹320, that's your real margin, not a guess.
Use actual purchase prices and update them: when steel goes from ₹72 to ₹80/kg, the bracket's material cost rises by ₹9.60.
Using the BOM to plan production
- Check materials for the order quantity against stock in the producing warehouse.
- Reserve them, so the same sheet isn't promised to two orders.
- Issue materials and record output when the run finishes: good units, rejected units, and what was really used.
- Compare actual with standard. If a run of 100 brackets used 132 kg instead of 120 kg, you have a scrap problem worth looking at.
Common BOM mistakes
- Quantities per batch instead of per unit, so every order is off by a factor.
- No scrap allowance, so the store always "loses" material.
- One BOM for variants. A bracket with and without paint needs two recipes.
- Never updated after a design change or a new supplier's material.
How KnowyourInventory handles BOMs
Recipes (BOMs) list materials, quantities, operations and overhead. Production orders check availability, reserve materials, and when completed use the materials and receive the finished goods in one step, with good and rejected units, actual usage and by-products. Each order shows planned versus actual use and its full cost. You can also ask ChatGPT: "Can we make 40 brackets this week?"
Frequently asked questions
What is a BOM in manufacturing?
A bill of materials is the complete list of raw materials, parts and sub-assemblies, with the quantity of each, needed to make one unit of a finished product. It's used to plan purchasing and production and to calculate product cost.
What is the difference between a BOM and a recipe?
They're the same idea. "Recipe" is common in food, chemicals and process industries; "bill of materials" in engineering and assembly. Both list inputs and quantities per unit of output.
Should the BOM include scrap?
Yes. Include the normal scrap or process loss in the quantity, so planned usage matches what the store really issues. Track abnormal scrap separately as rejected output.
Can I manage BOMs in Excel?
For a few products, yes. It breaks down when you need to check stock for many orders at once, reserve material, or compare planned and actual usage, because Excel doesn't connect the BOM to live stock.